Telecommunications Duct Bank Replacement
- Campus
- IU Bloomington
- Completion date
- December 2008
- Project type
- Renovation
- Primary use
- Utilities
- Architect
- MNA
- Team leader
- Koryta
Project budget
- Internal budget
- $2,000,000
- Total budget
- $2,000,000
Project description
This project involved the installation of a duct bank along the south edge of Seventh Street, along the west edge of Union Street, and through the west side of the parking lot east of Eigenmann Hall. A steel sleeve under the railroad was installed for routing conduits. Twenty four-inch ducts were installed in the duct bank.