McNutt North Asbestos Abatement

Campus
IU Bloomington
Completion date
July 2008
Project type
Renovation
Primary use
Student Residence
Architect
UAO
Team leader
Walter

Project budget

Internal budget
$3,921,899
Total budget
$3,921,899

Project description

Asbestos abatement was completed in 402 rooms of McNutt North Quadrangle on the IU Bloomington campus. The work included the removal of asbestos-containing material in an acoustical spray used on the ceilings of all student rooms, the addition of new leveling materials to conceal form marks on the concrete ceilings, and the application of a new gypsum-based spray.

McNutt North
McNutt North