Qualified Energy Savings Project
- Campus
- IU South Bend
- Completion date
- December 2012
- Project type
- Renovation
- Primary use
- Utilities
- Architect
- Team leader
- Matson
Project budget
- Internal budget
- $8,000,000
- Total budget
- $8,000,000
Project description
The primary objective of the Qualified Energy Savings Project (QESP) for Indiana University South Bend was to reduce utility and maintenance costs by upgrading and/or replacing selected electrical and mechanical systems in the buildings. The secondary objective included reducing maintenance costs of those systems as well as decreasing water and sewer expenses.