Bicentennial Repair and Rehabilitation Plan Indianapolis
- Campus
- IU Indianapolis
- Completion date
- April 2022
- Project type
- Major Renovation
- Primary use
- Academic
- Architect
- arcDESIGN - Health Sciences and Dunlap; Fanning Howey - Bryce and Ott
- Team leader
- Thompson - Health Sciences, Dunlap, Bryce, Ott
Project budget
- State funding
- $62,000,000
- External budget
- $4,000,000
- Total budget
- $66,000,000
Project description
This project, totaling $66,000,000, will renovate four buildings on the IU Indianapolis campus (Health Sciences, Dunlap, Bryce, Ott) and three buildings on the Bloomington campus (Mathers/Glenn A. Black [IUMAA], McCalla). Due to their age, these facilities require updated building systems (mechanical, electrical, plumbing, life safety, and fire protection). Exterior repairs and interior renovations will improve accessibility, efficiency, and safety.